Current Status

Team should update this status report every sprint.

Gitlab Board and issues

Status of sprint 00 Date 17.1.2025

What has been achieved

  • Team has been formed
  • Team Leader was selected
  • OPF Administrator was selected
  • Team has a name
  • Project working environment up and running
  • Home page updated
  • Status page updated

Status of sprint 01 Date 24.1.2025

What has been achieved

  • First daily scrum was held on 24th of January at 8:15 local time
  • Open issues were succesfully imported to the teams backlog
  • Team level discussion around open issues - delegating and prioritizing
  • CSC platform activated and cPouta succesfully launched

Next steps

  • Sprint planning
  • Task planning
  • Learning about EPICs and selecting them for the project
  • Communication plan
  • Risk management plan
  • Studying more about PrestaShop

Status of sprint 02 Date 7.2.2025

What has been achieved

  • EPICs selected
  • Started working on requirement specification documentation
  • Risk management plan finalized

Do we have a problems/challenges?

  • No issues detected

Next steps

  • Requirement specification documentation finalized
  • Project roadmap
  • Communication plan
  • Updating the website

Status of sprint 02 Date 7.2.2025

What has been achieved

  • Communication plan finished
  • Website updated

Next steps

  • Finalizing documentation to prepare for Gate 01 review

Status of sprint 02 Date 14.2.2025

  • Reviewed Sprint 02 issues
  • Docker pipelines passed succesfully
  • Working on documentation

Next steps

  • Finalizing documentation to prepare for Gate 01 review
  • Preparing for Sprint 03

Status of sprint 02 Date 14.2.2025

What has been achieved

  • Finalizing Sprint 03 issues
  • Finalized documentation for Gate 01 review

Next steps

Starting to work on EPICs Preparing for Sprint 04